August 6, 2016 Meeting Notes

The Future Home Committee met with Entheos Architects and Maxwell Construction on August 6. Kevin from Entheos reported that the traffic survey would be done for both the church activity as well as the school activity. The study will begin the week of August 22.

He also presented several plans for the entrance to the church from the gathering space. The committee asked for a couple of changes to the design. Toby from Entheos showed the changes that were requested by the committee at the last meeting for the Blessed Sacrament Chapel. Again, the committee asked for a few more changes.

Jeff from Maxwell presented the preliminary cost for the site work need prior to construction.
The committee looked at samples of brick and limestone for the exterior of the building. Kevin was asked to bring a few larger samples for the next meeting.

The next scheduled meeting is August 27.